Today BT have just completed installation of their tail circuit to provide additional connectivity to our NE5 Datacentre. This connection is provided directly to Telecity Harbour Exchange 6/7 (HEX6/7), and compliments our existing diverse connectivity to Manchester.
Between Christmas and New Year, Virgin Media also completed splice work on our primary connection to Manchester, which reduced our round-trip latency to 4ms to Manchester. The additional connection to London should provide round-trip latency in the region of 8ms to London from Newcastle.
Showing posts with label newcastle. Show all posts
Showing posts with label newcastle. Show all posts
Monday, 18 January 2010
Wednesday, 25 February 2009
Power Installation - NE5 Newcastle Datacentre

More photos from the civil works taking place to facilitate the installation of the power cabling from the substation to the NE5 Datacentre in Newcastle upon Tyne. Top shows on-site works by our Civil Engineering Contractor Roadtech in the rear car-park. Bottom shows trench works about 100 yds up from the site.
Labels:
colocation,
data centre,
datacentre,
newcastle,
power installation
Monday, 23 February 2009
Work begins on our Newcastle NE5 data centre!
Today saw the begining of work on site to install the new power supply for our Newcastle NE5 data centre. Contractors began dig work this morning ready for installation of a new underground power cable running from the site back to the nearby substation. Last week work was underway at the substation to install a new transformer ready for the increase in supply.When completed this will provide us with the 600KW of power required when the data centre is at full capacity.