Monday, 23 February 2009

Work begins on our Newcastle NE5 data centre!

Today saw the begining of work on site to install the new power supply for our Newcastle NE5 data centre. Contractors began dig work this morning ready for installation of a new underground power cable running from the site back to the nearby substation. Last week work was underway at the substation to install a new transformer ready for the increase in supply.

When completed this will provide us with the 600KW of power required when the data centre is at full capacity.

No comments:

Post a Comment